Colombia G3 Coal Power Plant Project Successfully Passed the Examination 72 Hours Running at Full Capacity to Enter Commercial Operation

Date:2015-9-21 10:14

Colombia time at 2:00 on September 12th, our construction EPC Project G3 fired power plant passed 72 hours running at full capacity assessment, the average hourly load of 167MW, environmental emissions targets to meet the statutory requirements during the evaluation, heat consumption reach contract targets.

 

September 15th and 16th, Colombia local media "The Herald" reported on the G3 project. At 0:00 on September 17th, G3 Power Station project entered commercial operation in Colombian power system.

TypeInfo: News Express